Orchiston Architects Ltd  
ARCHITECTURE & DISPUTE
RESOLUTION


The Construction Contracts Act 2002: 

 

The Key Issues

Payment Claims

Adjudication

Residential Construction Contracts

Risk Management Issues

 

The Key Issues

 

·    The Act applies to all New Zealand construction contracts entered into or renewed on or after 1 April 2003. 

 

·    It is intended to facilitate regular and timely payments in construction contracts.

 

·    It sets out defaults for the processing and payment of payment claims.

 

·    It requires contract disputes to be submitted to adjudication.

 

·    It applies differently to residential contracts and commercial contracts.

 

·    A Construction Contract includes ‘head’ (or main) contracts and sub contracts.

 

·    Construction Work includes construction of all kinds, but does not include materials suppliers, unless they are supplying pre-fabricated components custom-made for the site, for example joinery.  It does not include contracts for professional services. 

 

·    The provisions will affect Main Contractors in two ways:  their contracts with the Principal, and their contracts with Subcontractors (in which case the Main Contractor will be the “Principal” or “Payer”).

 

·    Subcontractors are now able to “leverage” timely payment because “Pay if paid” and “pay when paid” clauses are now illegal.

 

·    Payment claims not made in accordance with the requirements of the Act may lead to difficulties in collection.

 

·    Architects and others administering progress claims need to be aware that failing to either process them in due time or to use the correct procedure may expose their Principals to a liability for “overpayment”.

[top of page>>]

 

Payment Claims

 

1.  Progress Payments:  Parties are free to agree on the number, interval between, amount of, and due date for payment of progress payments.  For the main contract, these terms are set out in the standard (usually NZIA or NZS) conditions of contract.  For a subcontract, the terms will be set out in the subcontract agreement.  Where there are no such terms or agreements, the Act provides the default:  monthly claims, based on the period of work, the value of work done (including variations), the contract sum and any set rates in the contract, with payment within 20 working days after the claim is served.

 

2.   Payment Claim Procedures:  A payment claim must be in writing, identify the contract, the work done and the period to which it relates, indicate the claimed amount and the date on which it is payable, indicate how the amount was calculated, and state that it is made under the Act.  In the case of residential contracts, the claim must be accompanied by a copy of Form 1 as set out in the Regulations.

 

3.   A Payment Schedule is the payer’s response to a payment claim.  A payment schedule need not be issued if the payer pays the payment claim in full.  Otherwise, it must be in writing, identify the claim to which it relates, indicate the amount being paid, and the reasons for the difference.  A payment schedule must be issued by the payer within the timeframe set out in the conditions of contract (where there is no such agreement, the Act provides the default of 20 working days), failing which the payer will be liable for the full amount claimed. 

 

4.   The Architect’s (or Engineer’s) Role:  The CCA provides that the agreed terms of a contract can include a means of calculating a progress payment.  That might have been intended to cater for the role of the architect or other independent person administering the contract.  Historically, such a role was important in ensuring that the main contractor’s claim and the principal’s payment were assessed on a fair and equitable basis.  With the advent of the CCA, the situation is now that whilst the architect still has the task of checking and certifying the main contractor’s claim, the principal now has the right to reject that assessment and to then set the amount to be paid. 

 

            A progress payment certificate issued by the architect under the main contract will almost never equate to the main contractor’s claim, unless that claim has already deducted the usual contract retentions.  That being so, a payment schedule will nearly always be required, and that payment schedule can only be issued by the payer.

 

            This has made the processing of progress claims rather more awkward for the architect, but the procedure that is gaining general acceptance, and which has been incorporated in both NZS 3910 and NZIA SCC 2005 is as follows:

 

·        The contractor submits a payment claim to the architect with a copy to the principal (i.e. the “payer” under the CCA”.

·        The architect checks it, makes an independent assessment to arrive at the payment due, and issues a payment certificate, together with reasons supporting the assessment.  The terms included on the certificate provide that it may operate as a “provisional” payment schedule.

·        This is forwarded to both the contractor and the principal.

·        If, within due time, the principal does not alter the architect’s assessment, that “provisional” payment schedule is deemed to be the payment schedule as required to be issued by the principal under the CCA.  The sum thereon becomes the sum payable.

·        If, within due time, the principal wishes to alter the architect’s assessment, reasons must be given, and advised to the architect.  The architect - acting as agent for the principal and not in the independent role required by the terms of the contract - then issues the payment schedule setting out the sum that is to be paid. 

·        It is usual for the Contractor to issue a GST invoice for the amount of the payment schedule, but in all cases the due date for payment is set by the terms of the contract, or by the defaults in the CCA if the contract does not stipulate a time.

 

5.   Subcontracts:  In the case of a subcontractor’s payment claim, the main contractor will be the “payer” under the CCA, and to whom the subcontractor will be forwarding the payment claim.  The main contractor either pays the full value of the subcontractor’s payment claim, or issues a payment schedule setting out the lesser payment, with the reasons therefore, and makes payment of that sum.  In all cases the due date for payment is set by the terms of the contract, or by the defaults in the CCA if the contract does not stipulate a time.

 

6.   Failure to pay in part, or on time:  Where a claim has been short paid without specifying the reasons in a payment schedule, or is unpaid by the due date, then the sum claimed becomes a debt due enforceable in court.  Where the sum set out in the payment schedule is short paid or is unpaid by the due date, then the sum set out in the payment schedule becomes a debt due enforceable in court.  In addition, except in the case of residential contracts, the party whose claim has not been met is entitled (after giving five days notice) to suspend work and to a corresponding extension of time, but not to the costs related to this. 

 

7.   Pay-if-paid, and pay-when-paid provisions:  The Act bans any such provisions in a construction contract (or subcontract).

[top of page>>]

 

Adjudication:

 

1.  Adjudication is a confidential, binding, and enforceable dispute resolution by an independent person.  The determination must be acted upon even if it is later reviewed by the District Court or by dispute resolution provisions (eg arbitration) provided for in the contract.  The parties to a contract cannot opt out of adjudication

 

2.  Any party to a construction contract has the right to refer a dispute to adjudication.

 

3.  An adjudicator can determine any “dispute or difference that arises under a construction contract”. 

 

4.  Subject to natural justice, the adjudicator may use whatever procedures are suitable in reaching a determination. 

 

5.  An adjudication does not supplant other remedies and dispute resolution processes where they are provided for in the contract.  There is no chronological link between the dispute processes provided by the contract and adjudication – they could run in parallel and concurrently - except that the former will prevail over (i.e. may overturn) the latter. 

 

6.  An adjudication is initiated by written notice served by the claimant on the other party or parties to the contract.

 

                        (a)    The notice must be dated, describe the dispute, the parties, the contract, and the remedies sought.

 

                        (b)    In the case of residential contracts, the notice must be accompanied by a copy of Form 2 as set out in the Regulations.

 

7.   The adjudicator is selected either by agreement between the parties, or failing that, as set out in the Act.  An agreement on an adjudicator is not binding on the parties if the agreement was made before the dispute arose.

 

(a)    Within 5 working days of receiving the adjudicator’s notice of acceptance, the claimant must submit the claim to the adjudicator and the other parties. 

 

(b)   Within a further 5 working days, or further time that the parties may agree or the adjudicator allows, the respondent may respond likewise.

 

8.   The adjudicator may, with the written consent of all the parties, determine multiple related disputes at the same time. 

 

9.   The adjudicator may determine:

 

·           any monies payable

·           the dates by which payment is to be made;

·           any conditions to be satisfied prior to payment;

·           any rights and obligations of the parties arising out of a dispute.

 

10. The outcome of the adjudication will need to be followed through in other contract administration tasks unless or until it is superceded by events or the outcome of other dispute processes.

[top of page>>]

 

Residential Construction Contracts

 

1.  A Residential Construction Contract is where one of the parties to the construction contract is, or intends to be, a residential occupier of the building to which the contract applies.  However, each subcontractor in a residential contract will have a Commercial Construction Contract with the head contractor. 

 

2.  A copy of Form 1 of the Regulations is required to be submitted as part of the claim procedure.

 

3.  Some provisions of the Act do not apply to Residential Construction Contracts:

 

(a) The default progress payment provisions in the Act do not apply:  unless standard NZIA (or similar) conditions of contract are in force the terms of progress payments must be specifically described in residential construction contracts.

 

(b) Unless specifically provided for in the contract, a claimant (main contractor) does not have the right to suspend work when payment is not made in full, or is only partly made but without reasons given.  NZIA standard conditions of contract SCC1 provide for suspension but not the NZIA Small Works 2002 conditions commonly used for residential work. 

 

(c) A contractor is unable to seek a charging order over the land to secure payment.

[top of page>>]

 

Risk Management Issues

 

1.      Main Contractors will need to process claims from subcontractors properly, failing which they will be exposed to liability for the claimed amount irrespective of its justification.

 

2.      A Main Contractor’s failure to pay a subcontractor in full without issuing a Payment Schedule would give the subcontractor leverage over contract time, and (if an adjudication follows) the subcontractor could seek a charge over the site.  That may disrupt the financing arrangements of the Principal, and bring considerable pressure on the Contractor from the Principal.

 

3.      An architect or similar independent contract administrator failing to process payment claims properly, or in due time, may expose the Principal to liability for the claimed amount irrespective of its justification.  The contractor also gains leverage over contract time, and (if an adjudication follows) could seek a charge over the (non-residential) site:  that may disrupt financing arrangements. 

 

4.      The Act denies a Main Contractor on a residential project from suspending work for non-payment;  however, their subcontractors can still suspend subcontract work because they have a “commercial construction contract” with the Main Contractor. 

 

5.      The Act refers to suspension of “work” by the contractor, and thus allows the possibility of suspension of particular work – rather than the whole job - to leverage due payment.  If this tactic is used, it must be made very clear to all concerned, otherwise a dispute over late completion is sure to follow.

 

6.      Main Contractors should ensure that all their subcontractors are bound by the terms of the Main Contract, in particular, to co-ordinate the timing and terms of progress claims.  This is usually specified in the P&G section of a specification, but it would be sensible to reconfirm it when seeking each subcontract quote.

 

7.      The Principal may rightly avoid acting upon a non-conforming Payment Claim.  Whilst the contractor may (eventually) obtain recovery through adjudication, the quickest remedy would be to submit a complying Payment Claim – whether it be for the same or a different amount.

 

8.      Main Contractors on residential contracts should ensure that they provide the Principal with a copy of Form 1 of the Regulations when submitting a Payment Claim as a progress claim, failing which their claim may not be recognised, nor be enforceable.

[top of page>>]

Home

Copies of the Act and Regulations on the Web

 

The Act is available on the web at:

 

http://www.legislation.govt.nz/browse_vw.asp?content-set=pal_statutes&clientid=575110469&viewtype=contents

 

The Regulations are available on the web at:

 

http://www.legislation.govt.nz/browse_vw.asp?content-set=pal_regs

 

These notes are provided by Orchiston Architects Ltd, Architecture & Dispute Resolution, P.O. Box 9136 Wellington, ph 04 5627 438, based on information as at 20/08/06.  They remain the copyright of Orchiston Architects Ltd, and may be copied and redistributed if and only if reproduced in full without any change in content whatsoever to the notes, letterhead/logo, and this footer.  They are intended as a general guide only, and not specific advice:  the author accepts no responsibility for persons acting or not acting upon the information herein, and specific advice should be sought from the author or other suitable professional in respect of particular issues as and when required.